Mechanized Track Installation With Cutting-Edge Machinery For Mumbai-Ahmedabad Bullet Train Corridor

Mechanized Track Installation With Cutting-Edge Machinery For Mumbai-Ahmedabad Bullet Train Corridor

For 352 km of alignment in Gujarat & DNH, 704 km of track is to be laid on viaduct and two Bullet Train depots at Sabarmati and Surat.

Kamal MishraUpdated: Saturday, May 04, 2024, 03:04 PM IST
article-image
Mechanized Track Installation With Cutting-Edge Machinery For Mumbai-Ahmedabad Bullet Train Corridor |

The Mumbai-Ahmedabad Bullet Train project will have J-Slab track system based on the Japanese Shinkansen track system. This is for the first time, the J-slab ballastless track system is being used in India.

For 352 km of alignment in Gujarat & DNH, 704 km of track is to be laid on viaduct and two Bullet Train depots at Sabarmati and Surat. The entire process of track installation is mechanized with cutting edge machinery especially designed and manufactured as per Japanese specifications. Taking the initiative under Make-in-India (MII) policy, some of the machines are now being manufactured in India also. The track laying work in Gujarat is progressing well. More than 35,000 MT of rails and three sets (03) of track construction machinery have been received at Surat and Vadodara for the project.

The fleet of machines include rail feeder car, track slab laying car, CAM laying car and flash butt welding machine, which will be used for track construction works. The assembly, testing and commissioning of these machines is in progress.

Flash butt welding machine (FBWM)

The 25 m long 60 kg rails are welded using Flash butt welding machine (FBWM) to form 200 m long panels near the TCB (track construction base) over the viaduct. Total 3 FBWM have been procured till now, and the same have to pass through stringent approval methodology prior to commencement of Rail welding fit for allowing high speed train running at 320 kmph.

The training for rail weld finishing and rail weld testing have been completed by the JARTS.

Track Slab Laying Car (SLC)

Precast track slabs are lifted on to the viaduct, loaded on specially designed SLC and moved to the track laying location. By using SLC, which can pick 5 slabs at a time, track slabs are laid in position on the RC track bed. 3 SLC have been arranged for slab laying work.

Rail Feeder Car (RFC)

200 m long panels are fed and laid over RC track bed using Rail Feeder Car. RFC will push the rail pair over the RC bed and temporary track will be laid initially on RC. Total 4 RFC have been procured till now.

Cement Asphalt Mortar Injection Car (CAM Car)

After placement of track slabs at proper place on the RC Bed, CAM car runs on the parallel track. This CAM car mixes the ingredients for CAM mix in design proportion and this CAM mix is injected under the slab to achieve the required line and level of track. 2 CAM cars have been procured till now.

RECENT STORIES

Palghar Shocker: 22-Yr-Old Woman Hacks Husband To Death Using Axe; Arrested

Palghar Shocker: 22-Yr-Old Woman Hacks Husband To Death Using Axe; Arrested

Mumbai Murder: 89-Yr-Old Woman Killed, Decomposed Body Found In Malad House; Probe Underway

Mumbai Murder: 89-Yr-Old Woman Killed, Decomposed Body Found In Malad House; Probe Underway

Mumbai: BJP Candidate Mihir Kotecha Accuses Workers Of Sena UBT's Sanjay Dina Patil Of Vandalising...

Mumbai: BJP Candidate Mihir Kotecha Accuses Workers Of Sena UBT's Sanjay Dina Patil Of Vandalising...

'Country Would Witness De-Modination On June 4,' Says Shiv Sena UBT Chief Uddhav Thackeray During...

'Country Would Witness De-Modination On June 4,' Says Shiv Sena UBT Chief Uddhav Thackeray During...

Gujarat GST Commissioner Grabs 620 Acres From Entire Village Near Maharashtra's Mahabaleshwar

Gujarat GST Commissioner Grabs 620 Acres From Entire Village Near Maharashtra's Mahabaleshwar