Mumbai News: BMC Extends Mulund Dumping Ground Waste Processing Deadline To Feb 2026; 32 Per Cent Legacy Waste Still Pending

Mumbai News: BMC Extends Mulund Dumping Ground Waste Processing Deadline To Feb 2026; 32 Per Cent Legacy Waste Still Pending

Mumbai generates around 7,000 metric tonnes of waste daily, with 90% sent to the Kanjurmarg processing plant and 10% still dumped at the Deonar landfill. The 24-hectare Mulund dumping ground, operational since 1968 and once the city’s second-largest, was officially closed in 2018.

Shefali Parab-PanditUpdated: Saturday, December 06, 2025, 12:00 AM IST
article-image
Mulund landfill clearance deadline extended to Feb 2026; 32% waste yet to be processed. | Representational image

Mumbai, Dec 05: The BMC has once again extended the deadline for processing legacy waste at the Mulund dumping ground, pushing it to February 2026 — the third such extension.

Although the project to remediate nearly 78 lakh tonnes of accumulated waste officially began in 2021, progress has been hampered by COVID-19 disruptions and delays in obtaining key regulatory permissions. As a result, despite ongoing efforts, about 32% of the waste still remains to be processed.

Mulund Landfill: Status & Background

Mumbai generates around 7,000 metric tonnes of waste daily, with 90% sent to the Kanjurmarg processing plant and 10% still dumped at the Deonar landfill. The 24-hectare Mulund dumping ground, operational since 1968 and once the city’s second-largest, was officially closed in 2018.

In October that year, the BMC awarded a Rs 731-crore contract to reclaim the site through bio-mining, an eco-friendly method to process legacy waste and recover land. However, due to COVID-19-related delays and challenges in obtaining necessary permissions, actual work began only in 2021.

Progress So Far, Work Still Pending

Over the past five years, 78 lakh tonnes of waste, including about 56 lakh tonnes of legacy waste, has been cleared from the Mulund landfill. The remaining 21 lakh tonnes is expected to be bio-mined, with the site fully cleared within the next year. However, the contractor failed to complete the work by June 2025, and operations were further halted during the monsoon.

Also Watch:

Penalty Imposed for Delay

While the contractor had requested a one-year extension, the civic body has approved the deadline only until February 2026. “The contractor must complete the processing within this period. We have already imposed a fine of Rs 8 crore on him,” said a senior civic official.

To get details on exclusive and budget-friendly property deals in Mumbai & surrounding regions, do visit: https://budgetproperties.in/

RECENT STORIES

Mumbai Infra News: BMC Drops Plan To Demolish Goregaon’s Veer Savarkar Flyover For...
Mumbai Infra News: BMC Drops Plan To Demolish Goregaon’s Veer Savarkar Flyover For...
BMC Elections 2026 Results: Mahayuti Deadlock Over Mayor’s Post Pushes Mumbai Mayoral Poll To...
BMC Elections 2026 Results: Mahayuti Deadlock Over Mayor’s Post Pushes Mumbai Mayoral Poll To...
Trombay Police Book Lucknow CA For GST Fraud, ₹4.69 Crore Liability Imposed On Mumbai Shop Owner
Trombay Police Book Lucknow CA For GST Fraud, ₹4.69 Crore Liability Imposed On Mumbai Shop Owner
Bombay HC Refuses To Halt Redevelopment Of 75-Year-Old Municipal Buildings In Lower Parel, Says...
Bombay HC Refuses To Halt Redevelopment Of 75-Year-Old Municipal Buildings In Lower Parel, Says...
Maharashtra Politics: Proposal To Unite Rival Shiv Sena Factions For Solapur Rally Sparks Political...
Maharashtra Politics: Proposal To Unite Rival Shiv Sena Factions For Solapur Rally Sparks Political...