Mumbai: CAG points out 'abnormal delays' in obtaining clearances for setting up waste-to-energy plant at Deonar landfill

Mumbai: CAG points out 'abnormal delays' in obtaining clearances for setting up waste-to-energy plant at Deonar landfill

Only 10 percent of work on the project was completed by December 2022, the delays will affect the project schedule, said the report.

SHEFALI PARAB-PANDITUpdated: Monday, March 27, 2023, 09:57 PM IST
article-image
Mumbai: CAG points out abnormal delays in obtaining clearances for setting up waste-to-energy plant at Deonar landfill | Representational Image

The Comptroller and Auditor General (CAG) in its recent report has pointed out the poor monitoring and abnormal delays in obtaining mandatory clearances for setting up a waste-to-energy plant at the Deonar landfill. Only 10 percent of work on the project was completed by December 2022, the delays will affect the project schedule, said the report.

Report presented by Fadnavis in assembly

A special audit report on BMC, by the CAG, was presented in the Maharashtra legislative assembly by Deputy Chief Minister and Finance Minister Devendra Fadnavis Saturday. The audit also covered the investigation of the ambitious project undertaken by BMC's solid waste management department.

Delays in getting obtaining the mandatory clearances

"The BMC issued a global e-tender for setting up a waste-to-energy project with a capacity of 3,000 tonnes per day. But it was subsequently downsized to 600 tonnes per day. The work was awarded to M/s. Chennai MSW Pvt. ltd at a cost of Rs. 648 crores, while payment of Rs, 49.12 crores till date. However, poor monitoring by the BMC and abnormal delays in obtaining the mandatory clearances are likely to have a significant impact on the project delivery schedule," said the CAG report.

HC had ordred shutting Mulund and Deonar dumping grounds

The city produces around 6,200 tonnes of garbage daily. Dumping grounds in Mulund and Deonar were ordered to shut in 2016 after the High Court observed that they had reached saturation points.

After a major fire in 2015 at the dumping ground, the Central government and the Bombay High Court had ordered the BMC to come up with a scientific plan for waste disposal. The Deonar dumping ground was established in 1927 and is spread across 120 hectares. The oldest landfill in Mumbai has mountains of garbage reaching 18 floors high. So the BMC planned to start a waste-to-energy project in 2016, that will generate 4 megawatts of electricity. But it took years for the BMC to obtain environmental clearances from the Central government. Currently, 5,500 metric tonnes of garbage is sent to the processing plant at Kanjurmarg, and another 700 metric tonnes is dumped in the Deonar dump yard.

RECENT STORIES

Maharashtra Cyber Police Files FIR In Ranveer Singh Deepfake Video Case

Maharashtra Cyber Police Files FIR In Ranveer Singh Deepfake Video Case

Pregnancy Termination Case: Bombay HC Asks Medical Board’s Opinion On Selected Foetal Reduction

Pregnancy Termination Case: Bombay HC Asks Medical Board’s Opinion On Selected Foetal Reduction

Urdu Markaz: Single Platform To Refine Language Studies

Urdu Markaz: Single Platform To Refine Language Studies

Mumbai: Otters Club Staffer Seen Groping Child In CCTV Footage, Say Police

Mumbai: Otters Club Staffer Seen Groping Child In CCTV Footage, Say Police

Insurance Firm Rebuked: Widows Get Justice

Insurance Firm Rebuked: Widows Get Justice