35 years on, Mumbai Trans Harbour Link taking shape

35 years on, Mumbai Trans Harbour Link taking shape

The project has been divided into three packages. As on October 31, the Mumbai Metropolitan Region Development Authority (MMRDA) has completed 15 per cent of the work in the first package of the 10.4 km bridge.

Sweety Adimulam (DO NOT USE)Updated: Monday, December 02, 2019, 08:55 AM IST
article-image
35 years on, Mumbai Trans Harbour Link taking shape | Photo credits: roadtraffic-technology.com

Mumbai: The Mumbai Trans Harbour Link (MTHL), also known as the Sewri Nhava Sheva Connector, which was envisaged 35 years ago, its actual construction began only in March 2018. So far, only 14 per cent of the total work has been completed.

The project has been divided into three packages. As on October 31, the Mumbai Metropolitan Region Development Authority (MMRDA) has completed 15 per cent of the work in the first package of the 10.4 km bridge. About 12 per cent progress has been achieved in the second package, which includes the construction of a 7.8-km-long bridge, while in the third package, 11 per cent construction, including building a 3.8-km viaduct, has completed.

Once ready, the 22-km-long sea bridge, estimated to cost around Rs17,843 crore, will decongest the island city and improve connectivity between Mumbai and Navi Mumbai.

Apart from cutting the travel time and saving fuel, the MTHL sea bridge will accelerate the growth of the Navi Mumbai region, as it is expected to directly rationalise the real estate prices in Mumbai city. The deadline to complete the project is December 2020.

Talking to the FPJ about the project, Pravin Purav, an Uran resident and senior political journalist, said, “Once the sea link is ready, it will reduce the distance between Mumbai and Navi Mumbai. Not just commuters like me, but the farmers will also benefit from the route, making it easier to transport their crops to the main markets of the city fast. Currently, I travel by ferries from Mazgoan Dock to reach Uran. The ferry boats are available at a frequency of one and a half hours. It takes nearly 40 minutes to reach the destination, and costs Rs40 for a single trip. The monthly pass costs Rs1,500. I wish for the timely completion of the sea link, as the project has already delayed a lot. The sea link will definitely provide a major relief to commuters. Moreover, the bridge should be made toll-free.”

Commenting on the pace of the project and its completion, Dilip Kawathkar, the MMRDA joint project director (public Relations), said the work is going on efficiently despite facing several challenges.

RECENT STORIES

Mumbai News: 'We Spent ₹3 Crore To Ensure Fire Safety Compliance, But In Vain,' Say Tardeo...

Mumbai News: 'We Spent ₹3 Crore To Ensure Fire Safety Compliance, But In Vain,' Say Tardeo...

Ganeshotsav 2025: Idol Maker Booked For Cheating Devotee After Fleeing Without Delivering Ganesh...

Ganeshotsav 2025: Idol Maker Booked For Cheating Devotee After Fleeing Without Delivering Ganesh...

Mumbai Food Fraud: Crime Branch Seizes 550 Kg Fake Paneer Made From 'Cheese Analog' In Antop Hill...

Mumbai Food Fraud: Crime Branch Seizes 550 Kg Fake Paneer Made From 'Cheese Analog' In Antop Hill...

Mumbai Medical Breakthrough: K J Somaiya Hospital Treats 69-Year-Old’s 2 Rare Congenital Heart...

Mumbai Medical Breakthrough: K J Somaiya Hospital Treats 69-Year-Old’s 2 Rare Congenital Heart...

Mumbai Traffic Update: Elphinstone Bridge To Close From September 10 For Demolition, Part Of...

Mumbai Traffic Update: Elphinstone Bridge To Close From September 10 For Demolition, Part Of...