Mumbai News: 'Lifting Of 2 Barfiwala Spans Enough To Fix Gokhale Bridge Issue', Says IIT Bombay

Mumbai News: 'Lifting Of 2 Barfiwala Spans Enough To Fix Gokhale Bridge Issue', Says IIT Bombay

The BMC has also expedited the work on the second side of the Gokhale bridge, which is yet to be opened.

Shefali Parab-PanditUpdated: Tuesday, April 09, 2024, 01:07 AM IST
article-image
File

Instead of four, the lifting of two spans of the CD Barfiwala flyover will facilitate its alignment with the Gokhale bridge, said the Indian Institute of Technology Bombay (IIT- B) on Monday, while giving its opinion on the report submitted by the Veermata Jijabai Tecnological Institute (VJTI). The latter has recommended the jacking up of four spans, which would have cost Rs9 crore, to level the two metres gap between both the structures. With the IIT-B's suggested modification, one side of the bridge can be aligned with Rs3 crore.

“The alignment job can be done in 90 days as per the VJTI's report. We will expedite the work and complete it by June 30 to minimise the traffic congestion,” said a civic official. Currently, the BMC has prioritised the alignment of the north side of the bridge.

IIT-B and VJTI's Collaboration For Flyover Span Changes

In its report submitted to the BMC last month, the VJTI has proposed to lift the flyover's last four spans. However, the civic body approached the IIT-B for a second opinion and a site inspection, which would help it to take a final decision. After inspection of the site, the IIT-B principally agreed to the VJTI's, except for the said change. Accordingly, the latter will now prepare the drawings on the alignment of the bridges and will also oversee the work on the site, said civic sources.

BMC Accelerates Gokhale Bridge Construction

The BMC has also expedited the work on the second side of the Gokhale bridge, which is yet to be opened. All the girders are expected to arrive in Mumbai by April 22. Accordingly, the assembly work will be completed by the month's end, while the launching is expected in May, said the official. 

RECENT STORIES

Gangster Prasad Pujari Assaulted Inside Mumbai Central Jail; FIR Filed Against 7 Inmates Amid...

Gangster Prasad Pujari Assaulted Inside Mumbai Central Jail; FIR Filed Against 7 Inmates Amid...

'Even A Suspect Has Right To Liberty': Bombay HC Grants Bail, Terms Post-Sunset Arrest Illegal

'Even A Suspect Has Right To Liberty': Bombay HC Grants Bail, Terms Post-Sunset Arrest Illegal

Mall’s Structural Audit Done, Report Awaited: Link Square Premises Society Tells Bombay HC

Mall’s Structural Audit Done, Report Awaited: Link Square Premises Society Tells Bombay HC

FPJ Analysis: Maharashtra’s Public Security Bill Raises Alarm Over Civil Liberties, Lacks...

FPJ Analysis: Maharashtra’s Public Security Bill Raises Alarm Over Civil Liberties, Lacks...

Mumbai-Pune Highway Accident: Two Dead, Six Injured As Oversized Pipes Fall From Truck In Bhor Ghat

Mumbai-Pune Highway Accident: Two Dead, Six Injured As Oversized Pipes Fall From Truck In Bhor Ghat