Mumbai News: BMC Begins Demolition, Rebuild Of 7 Unsafe Bridges In Malad-Kandivali At ₹26.43 Crore; Check Details Of The Project

Mumbai News: BMC Begins Demolition, Rebuild Of 7 Unsafe Bridges In Malad-Kandivali At ₹26.43 Crore; Check Details Of The Project

The project is estimated to cost Rs. 26.43 crore and is expected to be completed within two years.

Shefali Parab-PanditUpdated: Saturday, July 12, 2025, 03:36 AM IST
article-image
Mumbai News: BMC Begins Demolition, Rebuild Of 7 Unsafe Bridges In Malad-Kandivali At ₹26.43 Crore; Check Details Of The Project |

Mumbai: Based on structural audit recommendations, the BMC has initiated demolition and reconstruction of seven bridges in the P North (Malad) and R South (Kandivali) wards. This includes three vehicular bridges and four foot over bridges (FOBs). The project is estimated to cost Rs. 26.43 crore and is expected to be completed within two years.

In 2023, M/s. Structronics Consulting Engineers Ltd. submitted their re-examination report of these bridges to the civic body. Subsequently, M/s. Femstruct Consulting Engineers Pvt. Ltd. prepared the design, planning, and cost estimates for the following bridges. It includes two FOBs near Mahalaxmi Dairy Farm and Hanuman Nagar (Kandivali East), the Gaodevi Road (Kandivali East), the FOB linking Narwane Transit Camp and nearby slums (Kandivali West), FOB near Ramnagar Chawl, Bihari Tekdi, and Kamaraj Chawl (Kandivali East), as well as the vehicular bridge in front of Surabhi Complex (Kandivali West), and at Appa Pada, Gandhi Tekdi (Malad–Kandivali East border).

Among these, the FOBs near Mahalaxmi Dairy Farm and Hanuman Nagar in Kandivali East, as well as the one at Kamaraj Chawl, are in a dilapidated condition and have been completely closed for pedestrians due to safety concerns. The remaining bridges are also structurally compromised and have been partially closed to vehicular or pedestrian traffic as a precautionary measure, as per civic official. Three companies submitted their bids for the bridge reconstruction project. 

M/s. Bucon Engineers and Infrastructure Pvt. Ltd. emerged as the lowest bidder, quoting 11% above the estimated cost of Rs. 19.66 crore. Following negotiations, the BMC finalised the contract at Rs. 26.43 crore. "As the scope includes two vehicular bridges, traffic diversions will be implemented in coordination with the traffic police to ensure smooth and safe movement in the affected areas during the construction period," an official added.

Foot Over Bridges (FOBs)

Mahalaxmi Dairy Farm: Length -18.80 metres, Width – 3 metres

Hanuman Nagar: Length – 18.80 metres, Width – 3 metres

Gaodevi Road: Length – 12 metres, Width – 9.5 metres

Narwane Transit Camp: Length – 13.76 metres, Width – 3 metres

Ramnagar Chawl, Bihari Tekdi: Length – 30.02 metres, Width – 3 metre

Vehicular Bridges

In front of Surabhi Complex:
 Length – 9 metres, Width – 16.40 metres

Appa Pada, Gandhi Tekdi:
 Length – 13.6 metres, Width – 21.3 metres

RECENT STORIES

Mumbai Crime: Girlfriend Arrested After 26-Year-Old Boyfriend’s Death In Dongri, ADR Converted To...

Mumbai Crime: Girlfriend Arrested After 26-Year-Old Boyfriend’s Death In Dongri, ADR Converted To...

Panvel Municipal Corporation Extends Abhay Yojana Deadline Until September 15, Offers 90% Waiver On...

Panvel Municipal Corporation Extends Abhay Yojana Deadline Until September 15, Offers 90% Waiver On...

Shiv Sena (UBT) Chief Uddhav Thackeray Extends Support To Manoj Jarange’s Maratha Quota Agitation,...

Shiv Sena (UBT) Chief Uddhav Thackeray Extends Support To Manoj Jarange’s Maratha Quota Agitation,...

Navi Mumbai News: NMMC Promotes Eco-Friendly Ganeshotsav 2025 With 143 Artificial Ponds, Floral...

Navi Mumbai News: NMMC Promotes Eco-Friendly Ganeshotsav 2025 With 143 Artificial Ponds, Floral...

Mumbai Crime: 56-Year-Old Share Trader Robbed Of Gold Ornaments Worth ₹5.1 Lakh Near...

Mumbai Crime: 56-Year-Old Share Trader Robbed Of Gold Ornaments Worth ₹5.1 Lakh Near...