Mumbai: MRVC’s Panvel-Karjat Suburban Railway Corridor Project Achieves 67% Progress, On Track For December 2025 Completion

Mumbai: MRVC’s Panvel-Karjat Suburban Railway Corridor Project Achieves 67% Progress, On Track For December 2025 Completion

This project, being executed by the Mumbai Railway Vikas Corporation (MRVC), is set to bring transformative connectivity to the region, linking Panvel and Karjat through a modern double-line corridor. MRVC aims to Complete Project by December 2025.

Kamal MishraUpdated: Friday, November 29, 2024, 12:25 AM IST
article-image
Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025 | File Photo

Mumbai: The much-anticipated Panvel-Karjat Suburban Railway Corridor, part of the ambitious Mumbai Urban Transport Project (MUTP-III), is making significant headway, inching closer to its targeted completion.

This project, being executed by the Mumbai Railway Vikas Corporation (MRVC), is set to bring transformative connectivity to the region, linking Panvel and Karjat through a modern double-line corridor. MRVC aims to Complete Project by December 2025.

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025 | File Photo

With a sanctioned cost of Rs 2,782 crore, the project has already achieved substantial progress both in terms of physical and financial execution. As of October 2024, the project boasts a 67% progress.

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025 | File Photo

“Once completed, the Panvel-Karjat Suburban Railway Corridor will significantly reduce travel time, provide seamless connectivity, and cater to the increasing commuter demand in the Mumbai Metropolitan Region (MMR). By serving as a crucial link between Panvel and Karjat, the corridor will support Mumbai's ever-expanding suburban railway network and promote regional economic growth” said Subhash Chand Gupta, Chairman and Managing Director, Mumbai Railway Vikas Corporation Ltd.

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025 | File Photo

Key Milestones Achieved

Land Acquisition and Approvals

-Private Land: 56.82 hectares of private land required for the project have been acquired, with possession fully received.

Government Land: All 4.4 hectares of required government land have been acquired.

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025 | File Photo

Forest Land: Permissions for Stage I forest clearance have been obtained, and work has commenced in forested areas. For Stage II clearance, key approvals have been secured, and the proposal is under advanced processing with the concerned authorities.

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025

Progress of the Panvel-Karjat Suburban Railway Corridor under Mumbai Railway Vikas Corporation, nearing completion by December 2025 | File Photo

Engineering Achievements

Earthworks- A massive 2 million cubic meters of earthwork filling has been completed.

Tunnels- Breakthroughs for all three tunnels have been achieved, with over 3,100 meters of underground excavation completed and lining works underway.

Bridges- Out of a total of 47 bridges, 29 minor and 6 major bridges have been completed.

Road Over Bridges (ROBs): 4 ROBs are complete, with significant progress on key structures at Mohape and Kirawali

Pune Expressway Underpass: A crucial component, involving girder launches, has been completed, with painting and final works also finished.

Station Infrastructure

Station Buildings- Construction of station and service buildings is advancing across Panvel, Chikhale, Mohape, Chowk, and Karjat stations.

Facilities- Utility structures, including platforms, foot overbridges (FOBs), and administrative buildings, are progressing steadily.

RECENT STORIES

Mumbai Local Train Services Disrupted By Technical Snag Near Andheri On July 17; Peak-Hour Commuters...

Mumbai Local Train Services Disrupted By Technical Snag Near Andheri On July 17; Peak-Hour Commuters...

Navi Mumbai News: Lingayat Community Protests In Vashi, Demands Independent Economic Development...

Navi Mumbai News: Lingayat Community Protests In Vashi, Demands Independent Economic Development...

Airoli–Kalwa Elevated Rail Project Hits Land, Rehab Hurdles; MRVC Targets Completion After R&R

Airoli–Kalwa Elevated Rail Project Hits Land, Rehab Hurdles; MRVC Targets Completion After R&R

Mumbai: Over 1,500 Loudspeakers Removed From Religious Place; Many Muslims Turn To Tech For Azaan...

Mumbai: Over 1,500 Loudspeakers Removed From Religious Place; Many Muslims Turn To Tech For Azaan...

Navi Mumbai Joins India’s Elite 'Super Swachh League' In Swachh Survekshan 2024, Sets National...

Navi Mumbai Joins India’s Elite 'Super Swachh League' In Swachh Survekshan 2024, Sets National...