Mumbai: MLA Ameet Satam Reviews Andheri's Gokhale Bridge Progress; May 2025 Opening Expected After Delays

Mumbai: MLA Ameet Satam Reviews Andheri's Gokhale Bridge Progress; May 2025 Opening Expected After Delays

MLA Ameet Satam, along with civic officials and contractors, conducted a review of Andheri's Gopal Krishna Gokhale bridge. Currently, the work is focused on the approach road and pillar erection on this critical east-west connector. However, the bridge is now expected to be open for traffic in May, a slight delay from the earlier commitment to open it by the end of April.

Shefali Parab-PanditUpdated: Saturday, February 01, 2025, 02:35 AM IST
article-image
MLA Ameet Satam reviews the progress of Andheri's Gokhale Bridge, with a May 2025 opening now expected after delays | File Photo

Mumbai: On Friday, local MLA Ameet Satam, along with civic officials and contractors, conducted a review of Andheri's Gopal Krishna Gokhale bridge. Currently, the work is focused on the approach road and pillar erection on this critical east-west connector.

However, the bridge is now expected to be open for traffic in May, a slight delay from the earlier commitment to open it by the end of April. The deadline for completion of the bridge has extended several times in the last two years.

The lowering of the second girder at Gokhale Bridge was completed on December 26, following the successful launch of the southern girder in September. While the work was initially slated to be finished by the end of November, it was delayed by over a month.

MLA Ameet Satam reviews the progress of Andheri's Gokhale Bridge, with a May 2025 opening now expected after delays

MLA Ameet Satam reviews the progress of Andheri's Gokhale Bridge, with a May 2025 opening now expected after delays | File Photo

This setback impacted the completion of the railway portion of the bridge, which was originally expected to be ready by December 31. The repeated deadline extensions have led to growing frustration among local residents and commuters, who have been facing inconvenience due to the delays.

Following a joint visit by the local MLA and civic officials, Satam provided an update on the ongoing work at the bridge. He reported that on the east side, all four foundations and piers have been completed, with one of the four girders successfully landed.

MLA Ameet Satam reviews the progress of Andheri's Gokhale Bridge, with a May 2025 opening now expected after delays

MLA Ameet Satam reviews the progress of Andheri's Gokhale Bridge, with a May 2025 opening now expected after delays | File Photo

On the west side, all five foundations and piers are finished, and two out of the three girders have been installed. "Work has been carried out on a war footing, and we are on track to open the bridge for traffic in May," said Satam.

A senior official said, "We had already warned the contractor that a Rs. 3 crore fine would be imposed if the work wasn't completed by November 15. Given the continued delays, the fine will now be recalculated based on the additional days of delay, with further penalties imposed accordingly."

The bridge was declared dilapidated and closed in November 2022. The BMC initially aimed to open two lanes for traffic after launching the first girder by May 2023, but the project was delayed by 10 months. The first half of the bridge finally became operational on February 26, 2024.

RECENT STORIES

Navi Mumbai News: 35-Year-Old Koparkhairane Teacher Sent To Judicial Custody For Obscene Video Chats...

Navi Mumbai News: 35-Year-Old Koparkhairane Teacher Sent To Judicial Custody For Obscene Video Chats...

Maharashtra News: Raigad District Collector Kishan Jawale Bans Heavy Vehicles On 8 Bridges After...

Maharashtra News: Raigad District Collector Kishan Jawale Bans Heavy Vehicles On 8 Bridges After...

Bombay HC Raps Police For Forcing Doctors To Reveal Minor’s Identity In MTP Cases Despite Supreme...

Bombay HC Raps Police For Forcing Doctors To Reveal Minor’s Identity In MTP Cases Despite Supreme...

Maharashtra To Cancel Fake Birth Certificates Of Illegal Bangladeshi Nationals By August 15

Maharashtra To Cancel Fake Birth Certificates Of Illegal Bangladeshi Nationals By August 15

Mumbai News: Saki Naka Social Activist Urges BMC Chief Bhushan Gagrani To Implement Permanent...