Mumbai-Ahmedabad Bullet Train Project: '80 Per Cent Of Excavation Work At BKC Station Completed,' Says NHSRCL

Mumbai-Ahmedabad Bullet Train Project: '80 Per Cent Of Excavation Work At BKC Station Completed,' Says NHSRCL

From deep urban shafts to mountain tunnels and marine crossings, the Bullet Train project is progressing fast, with 80 per cent of excavation work completed at the Bandra Kurla Complex (BKC) station in Mumbai, an official release said on Saturday.

PTIUpdated: Saturday, July 05, 2025, 05:49 PM IST
article-image
Excavation in progress at the BKC station site for India’s first Bullet Train project, 100 feet below ground | File Photo

Thane, Jul 5: From deep urban shafts to mountain tunnels and marine crossings, the Bullet Train project is progressing fast, with 80 per cent of excavation work completed at the Bandra Kurla Complex (BKC) station in Mumbai, an official release said on Saturday.

Of the 21-km-long underground and undersea tunnel between BKC and Shilphata in Thane district, 16 km is being excavated using Tunnel Boring Machines and 5 km with the help of the New Austrian Tunnelling Method, said the National High-Speed Rail Corporation of India Limited (NHSRCL) in the release.

The NHSRCL, which is implementing the 508-km rail corridor between Mumbai and Ahmedabad, said that base slab casting has already commenced at both ends of the BKC station site, at a depth of 100 feet below ground level.

About 80 per cent of the excavation work at the station has been completed, it said.

Base slab casting has been completed at Vikhroli (56 metres deep) and Sawli shaft (39 metres deep). These shafts are essential for launching tunnel boring machines and facilitating underground work, the release said.

Work on the Thane, Virar, and Boisar elevated stations in Maharashtra is progressing at an accelerated pace, it said, adding that pier work is being executed at multiple locations, with approximately 44 kilometres of piers cast so far.

In the Palghar district, excavation of seven mountain tunnels is underway, and construction has commenced on bridges across Vaitarna, Ulhas, and Jagani rivers, NHSRCL said.

The total cost of the project is pegged at Rs 1.08 lakh crore, and as per the shareholding pattern, the Government of India is to pay Rs 10,000 crore to the NHSRCL, while the two states involved, Gujarat and Maharashtra, are to pay Rs 5,000 crore each. The rest is to be paid by Japan through a loan at 0.1 per cent interest.

(Disclaimer: Except for the headline, this article has not been edited by FPJ's editorial team and is auto-generated from an agency feed.)

RECENT STORIES

Mumbai Sees Spike In Abandoned Newborn Cases As Police, CWCs Step In To Rescue Infants And Ensure...

Mumbai Sees Spike In Abandoned Newborn Cases As Police, CWCs Step In To Rescue Infants And Ensure...

Mumbai Crime News: Driver Arrested For Drugging, Raping & Blackmailing Domestic Worker Using Obscene...

Mumbai Crime News: Driver Arrested For Drugging, Raping & Blackmailing Domestic Worker Using Obscene...

Mumbai: MSRTC Senior Clerk Arrested For Embezzling ₹21.80 Lakh Meant For Tax Payments

Mumbai: MSRTC Senior Clerk Arrested For Embezzling ₹21.80 Lakh Meant For Tax Payments

Powai Hostage Case: Mumbai Crime Branch Awaits Crucial FSL Report In Sensational Kidnapping Of 17...

Powai Hostage Case: Mumbai Crime Branch Awaits Crucial FSL Report In Sensational Kidnapping Of 17...

Mumbai News: Man Drowns In Water Tank Of MHADA Building In Wadala

Mumbai News: Man Drowns In Water Tank Of MHADA Building In Wadala