Mumbai: Porous Stones, Ageing Masonry Joints Behind CSMT Dome Leak; Experts Roped In For Heritage Repairs
Water leakage from the iconic dome of Mumbai's CSMT during restoration has been traced to porous stones and ageing masonry joints, the RLDA said. Experts from VJTI and heritage conservation specialists are finalising a repair plan that preserves the UNESCO site's original character. Restoration work is underway and is expected to be completed by August 31, 2026.

Mumbai: Porous Stones, Ageing Masonry Joints Behind CSMT Dome Leak; Experts Roped In For Heritage Repairs | Wikimedia
Mumbai: The leakage reported from the iconic dome of Mumbai's Chhatrapati Shivaji Maharaj Terminus (CSMT) during the ongoing restoration work has been traced to porous stones and ageing masonry joints, according to the Rail Land Development Authority (RLDA). The authority said the issue has been identified and experts from Veermata Jijabai Technological Institute (VJTI), conservation specialists and industry professionals have been consulted to restore the heritage structure without compromising its original character.
The UNESCO World Heritage Site is undergoing restoration of its heritage building and office spaces. During the ongoing monsoon, water seepage was noticed from parts of the historic dome, prompting concerns over the conservation work. RLDA clarified that the leakage was not caused by a single defect but by water entering through stone masonry joints and naturally porous stones that have weathered over time.
ALSO READ
According to RLDA, stone joints have already been treated using lime-and-jaggery-based grout and gravity grouting, a traditional conservation technique recommended by the Mumbai Heritage Conservation Committee (MHCC). However, sealing porous stones requires specialised treatment that complies with heritage conservation norms. For this, RLDA has sought technical inputs from VJTI's structural consultants, domain experts and conservationists affiliated with MHCC to finalise the appropriate methodology and material composition.
"Leakage in the domes of the heritage building at CSMT is an identified issue. The work for attending to and rectifying the leakage has been entrusted to RLDA. The work is in progress and will be completed by August 31, 2026," the authority said.
The incident underlines the technical complexity of restoring century-old heritage structures, where conventional waterproofing methods cannot be used and every intervention must preserve the building's historic fabric. The success of the repairs will be closely watched as CSMT remains one of Mumbai's most significant architectural landmarks and among the busiest railway stations in the country.
To get details on exclusive and budget-friendly property deals in Mumbai & surrounding regions, do visit: https://budgetproperties.in/
RECENT STORIES
-
Central Bank Of India Holds Nationwide MSME Credit Outreach, Mumbai Event Highlights Seven Lending... -
Sensex Jumps 898 Points As Banks Lead Rally, Nifty Closes Above 25,800 On Foreign Inflow Hopes -
Apple To Build Proactive AI Agent to Challenge Meta, OpenAI & Google -
'Sabse Zyada Dukhad Khabar': Kangana Ranaut Mourns Demise Of Yogi Adityanath's Mother Savitri Devi -
Mumbai This Weekend: From A Bhakti Concert To A Classic Car Rally, 5 Events To Check Out