Mumbai: Only 51% Of BMC’s Massive Civic Budget Spent So Far, Crores Lie Unused As Financial Year Nears End
The Brihanmumbai Municipal Corporation has spent only 51 per cent of its Rs 43,162-crore capital outlay for FY 2025–26, with a month left in the financial year. Funds meant for roads, health and education projects remain largely unutilised due to tendering delays and technical hurdles, raising concerns over a rushed year-end spending spree.

Mumbai: Only 51% Of BMC’s Massive Civic Budget Spent So Far, Crores Lie Unused As Financial Year Nears End |
Mumbai: The Brihanmumbai Municipal Corporation (BMC) had made a record provision of Rs 43,162 crore for civic amenities in its 2025–26 budget of Rs 74,427 crore, but with barely a month left for the financial year to end, only around 51 per cent of the allocated funds have actually been spent. The slow pace of expenditure has once again raised concerns over planning gaps and administrative delays during the ongoing period of bureaucratic rule.
Data available till January 31, 2026, shows that of the total capital expenditure provision of Rs 43,162 crore, the civic body has managed to spend only about Rs 22,425 crore, as reported by Marathi news portal, ESakal. Large portions of the remaining funds continue to lie idle in the BMC’s coffers, even as several key infrastructure and public service projects remain incomplete.
The budget, presented in February last year, had placed major emphasis on cement concrete roads, the Coastal Road project, sewage treatment plants and strengthening health infrastructure. However, officials admitted that a major portion of the funds earmarked for roads and bridges could not be utilised due to technical hurdles, tendering issues and procedural delays.
Several Works Still Pending
Despite heavy allocations to make Mumbai’s roads pothole-free, more than 45 per cent of road works are still pending. Action against contractors and repeated re-tendering processes have slowed execution on the ground. In the health department, nearly 60 per cent of the funds meant for upgrading suburban hospitals and procuring medicines remain unspent, according to the report. Similarly, in the education department, projects related to repairing municipal school buildings and setting up digital classrooms are stuck in the tendering stage.
Rush In March Raises Quality Concerns
With nearly 49 per cent of the budget still unspent, the civic administration is expected to fast-track works in March to utilise the remaining funds. However, activists have warned that the year-end rush to clear bills and complete projects could compromise quality. Social activist advocate Godfrey Pimenta cautioned that hurried execution at the end of the financial year often leads to substandard work, defeating the very purpose of the massive budgetary provisions.
To get details on exclusive and budget-friendly property deals in Mumbai & surrounding regions, do visit: https://budgetproperties.in/
RECENT STORIES
-
Asian Games 2026: Abhishek Sharma Unleashes Blistering 61 Off 28 With 7 Sixes Against Pakistan,... -
'Ye Kya Hogaya': Netizens React After Virat Kohli Gets Clean Bowled For Golden Duck In IND Vs WI 3rd... -
Nora Fatehi Takes Over Louboutin's Paris Fashion Week Show In Chocolate-Brown Mini Look, Cherry-Red... -
Maihar Road Accident: Damoh Brothers Returning From Gaya After Ancestors' Pind Daan Crash Into Road... -
Asian Games 2026: Indian National Anthem Plays In Aichi-Nagoya As Shreyas Iyer & Co Receive Gold...