Mumbai Infra Update: BMC Accelerates 337 MLD Ghatkopar STP Work, Full Project Targeted By March 2027
The BMC is accelerating work on its 337 MLD Ghatkopar sewage treatment plant, with the secondary-treatment liquid pipeline targeted for completion by December 31, 2026, and the full project by March 31, 2027. The workforce has been increased to around 1,000, while treated water will be reused and the project is expected to improve coastal water quality.

Around 1,000 workers are now deployed at the Ghatkopar sewage treatment project as the BMC pushes to meet its 2027 completion deadline | File Photo
Mumbai, October 8, 2026: At a time when every drop of water is becoming increasingly precious for Mumbai, the BMC has stepped up work on the 337-million-litre-a-day (MLD) sewage treatment plant (STP) at Ghatkopar.
The civic body has set a December 31, 2026 deadline for completing the liquid pipeline required for secondary treatment of sewage, while the entire project is targeted for completion by March 31, 2027.
Ghatkopar STP Work Accelerated
The BMC is developing a Ghatkopar STP using Sequential Batch Reactor (SBR) technology. "The treated water will be reused for various purposes, while the project is expected to improve coastal water quality and support marine ecosystems. Residents of Ghatkopar, Mankhurd, Govandi and Chembur are set to benefit from the project," said a civic official.
Additional Municipal Commissioner (Projects) Abhijeet Bangar inspected the project site on Thursday. To accelerate the project, the workforce at the site has been increased to around 1,000 personnel from the first week of October. Officials have directed that the additional manpower be maintained until the project is completed, ensuring work progresses at the required pace.
"To ensure the project is completed within the stipulated timeline, all works must be executed simultaneously and at an accelerated pace," directed Bangar. He stressed that quality, safety and efficiency must remain the top priorities at the worksite.
Seven STPs Under Construction
The BMC is constructing seven STPs at Worli (500 MLD), Bandra (360 MLD), Malad (454 MLD), Ghatkopar (337 MLD), Dharavi (418 MLD), Bhandup (215 MLD) and Versova (180 MLD), offering a combined treatment capacity of 2,464 MLD per day. Along with the operational 37 MLD Colaba STP, Mumbai’s total sewage treatment capacity will rise to 2,501 MLD.
Also Watch:
This ambitious project to upgrade seven STPs—stalled for nearly two decades—was awarded in May 2022 at a cost of Rs 27,309.83 crore.
To get details on exclusive and budget-friendly property deals in Mumbai & surrounding regions, do visit: https://budgetproperties.in/
RECENT STORIES
-
Mumbai Infra Update: BMC Accelerates 337 MLD Ghatkopar STP Work, Full Project Targeted By March 2027 -
Mumbai Fire At BMC Labour Camp In Mulund East Triggers Cylinder Explosions, 300 Workers Escape... -
Mumbai Infra Update: Vidyavihar Flyover Major Works Completed, Set To Open For Traffic By October 10 -
Delhi: 17-Year-Old Allegedly Drives Rented Audi, Crashes Into 3 Vehicles, Kills Pedestrian -
Woman Escapes Through Window With Son After Finding Crocodile Inside Home In Ratlam