Mumbai-Ahmedabad Bullet Train Project: Over 76,000 Segments To Be Cast For 16 Km Long Tunnel Between BKC-Shilphata
Of the total length, 16 kilometers will be excavated using three Tunnel Boring Machines (TBMs), while the remaining 5 kilometers will be constructed using the New Austrian Tunnelling Method (NATM).

Mumbai-Ahmedabad Bullet Train Project: Over 76,000 Segments To Be Cast For 16 Km Long Tunnel Between BKC-Shilphata | File/ Representative Pic
Mumbai: A 21-kilometer tunnel is under construction between the Bandra Kurla Complex and Shilphata for the Mumbai-Ahmedabad Bullet Train Project. Of the total length, 16 kilometers will be excavated using three Tunnel Boring Machines (TBMs), while the remaining 5 kilometers will be constructed using the New Austrian Tunnelling Method (NATM).
To construct the 16-kilometer section with TBMs, 76,940 segments will be cast to form 7,441 rings. Special ring segments are being cast for the tunnel lining, each ring comprising nine curved segments and one key segment, with each segment being 2 meters wide and 0.5 meters thick, a release issuedby the National High Speed Railway Corporation Ltd (NHSRCL) said.
High-strength M70 grade concrete is being used to ensure superior structural integrity and long-term durability. The casting and stacking yard, covering an area of 98,898 sqm (9.9 hectares) in Mahape, Thane district, Maharashtra, is currently being commissioned. The yard will feature nine sets of moulds, each containing ten pieces. Four sets of these moulds are already being installed on-site.
ALSO READ
The yard is equipped with various cranes, gantries, and machines to automate and mechanize the casting operations, ensuring high-quality assurance during the casting and stacking of the segments. Additionally, the facility will include casting sheds, a stacking area, a batching plant, and a steam curing area.
RECENT STORIES
-
Inside Isha Malviya's Amritsar Diaries: From Visiting Golden Temple To Street Shopping -
Video: After Mohammed Siraj, Nitish Kumar Reddy Celebrates Zak Crawley's Wicket Aggressively On Day... -
ITR Refund Delay Explained, Know The Key Reasons Behind The Hold-Up -
2 Killed, 2 Critical After Car Falls From British-Era Bridge On Indore-Betul Highway -
GGSIPU Offers Admissions To International Dual Degree Programme With AGH University; Details Here