MahaRERA Directs Developer To Fix Structural Defects At Andheri’s Vasant Oasis Jolan Society; Warns Of Penal Action For Non-Compliance
In its final order, MahaRERA directed the promoters of M/s. Neepa Real Estate Pvt. Ltd. to rectify all structural defects in the society’s building, specifically those in the common areas detailed in the complaint.

MahaRERA | File
The Maharashtra Real Estate Regulatory Authority (MahaRERA) has partly allowed a complaint filed by the Vasant Oasis Jolan Cooperative Housing Society Ltd. against developer M/s. Neepa Real Estate Pvt. Ltd. and its directors.
In its final order, MahaRERA directed the promoters of M/s. Neepa Real Estate Pvt. Ltd. to rectify all structural defects in the society’s building, specifically those in the common areas detailed in the complaint. The Authority also cautioned that any non-compliance would be viewed seriously and that penal action under Section 63 of the Real Estate (Regulation and Development) Act, 2016 (RERA) could be initiated against the defaulting party.
Complaint Filed by the Society
The complaint, filed by advocate Anil D’Souza on behalf of the Andheri (Marol)-based Vasant Oasis Jolan Cooperative Housing Society Ltd., sought several directions from MahaRERA. These included necessary repairs, the handover of the “Kitchen Area” on the S level, removal of car parking at the P1 and P2 gates, installation of a separate filtering system, and an extension of the warranty period for any structural defects.
Partial Relief Granted
While MahaRERA directed the developer to resolve the structural issues, it rejected other claims at this stage. Specifically, the claim raised by the society concerning common amenities, including the “Kitchen Area,” was termed premature.
ALSO READ
Furthermore, the Authority noted that the issue regarding the Sewage Treatment Plant (STP) was considered “non-surviving,” as the developer had already installed a new STP near Building No. 12 a fact not denied by the complainant.
Cooperation Directed
MahaRERA has directed the complainant-society to extend full cooperation to the developer for the execution of the repair work to ensure timely completion.
RECENT STORIES
-
JNU Election Result 2025: Tight Contest As Counting Underway For Key Posts; Who Will Win? Results... -
Edtech Unicorn PhysicsWallah Fixes Price Band For Upcoming IPO, Aiming For Valuation Of ₹31,500... -
Solar Modules Maker Emmvee Photovoltaic Power Announces Price Band For ₹2,900-Crore IPO -
Utah University Expands Police Force After Charlie Kirk Assassination Backlash -
Anunay Sood, 32-Year-Old Dubai-Based Travel Influencer & Photographer, Dies