Indian Railways Set To Transform Mumbai's Transportation Network With 301.5 km Of New Rail Projects Worth ₹16,240 Crore; Full Details Inside

The details of Multiple Railway Projects under various stages of execution in Mumbai are Projects in Central Railway and Western Railway; read full story to know the details

Add FPJ As a
Trusted Source
Indian Railways Set To Transform Mumbai's Transportation Network With 301.5 km Of New Rail Projects Worth ₹16,240 Crore; Full Details Inside
Kamal Mishra Updated: Friday, October 11, 2024, 01:25 AM IST
Indian Railways Set To Transform Mumbai's Transportation Network With 301.5 km Of New Rail Projects Worth ₹16,240 Crore; Full Details Inside

Indian Railways | Representative Image

Indian Railways is all set to change the face of transportation network in Mumbai by construction / extension of rail routes and upgradation of existing services through various Railway Projects covering a total stretch of 301.5 kms at a total estimated cost of Rs.16.240/- crores.

The details of Multiple Railway Projects under various stages of execution in Mumbai are as follows:

Projects on Central Railway

 1. CSMT-Kurla 5th & 6th line Project

 Project details: The CSMT-Kurla 5th & 6th line project under MUTP-II covering  a length of 17.5 track kilometres at an estimated cost of Rs.891 crores is under execution in two phases.

Phase-I is from Parel to Kurla covering 10.1 kms with a Target Date of Completion   by December-2025.

Phase –II is from Parel to CSMT covering 7.4 kms.

 Benefits: 

2. Panvel-Karjat Suburban Corridor Project

Project details: The Panvel-Karjat Suburban Corridor project under MUTP-III covering  a length of 29.6 track kilometres at an estimated cost of Rs.2,782 crores is under execution. This project is being executed by MRVC.

Earth work and work on tunnelling and bridges is in progress with a Target Date of Completion  by December-2025.

Benefits: 

3. Kalyan - Asangaon 4th line Project

Project details: The Kalyan - Asangaon 4th line project under MUTP-III-A covering  a length of 32 track kilometres at an estimated cost of Rs.1,759 crores is under execution..

Work of land acquisition is in progress  with a Target Date of Completion  by December-2026.

Benefits: 

4. Kalyan - Badlapur 3rd  & 4th line Project

Project details: The Kalyan - Badlapur 3rd  & 4th line project under MUTP-III-A covering  a length of 14.05 track kilometres at an estimated cost of Rs.1,510 crores is under execution. This project is being executed by MRVC.

Work of Utility shifting, Earth work and Bridge work  is in progress with a Target Date of Completion  by December-2025.

Benefits: 

5. Kalyan – Kasara  3rd  line Project

Project details: The Kalyan – Kasara  3rd  line project by Central Railway,  covering  a length of 67 track kilometres at an estimated cost of Rs.792 crores is under execution in two phases.

Phase-I is from Asangaon to Kasara with a Target Date of Completion  by February-2025 &

Phase –II is from Kalyan to Asangaon with a Target Date of Completion  by December-2025

Benefits: 

6. Airoli-Kalva (elevated) suburban corridor link Project

Project details: The Airoli-Kalva (elevated) suburban corridor link project under MUTP-III covering  a length of 3.3 track kilometres at an estimated cost of Rs.476 crores is under execution in two phases.

Under Phase-I commissioning of Digha Gaon station has been completed in January-2024  &

Under Phase –II work of land acquisition is in progress. This project is being executed by MRVC.

Benefits: 

7. Nilaje-Kopar double chord line Project

Project details: The Nilaje-Kopar double chord line is a project by Central Railway, covering a length of 5 track kilometres at an estimated cost of Rs.338 crores. Work for the same is currently in progress.

Benefits: 

Projects on Western Railway

1. Mumbai Central-Borivali 6th line Project

Project details: The Mumbai Central-Borivali 6th line project under MUTP-II covering  a length of 30 track kilometres at an estimated cost of Rs.919 crores is under execution in two phases.

Under Phase-I commissioning of Khar- Goregaon (8.9 kms) has been completed &

Under Phase –II work is in progress for the Goregaon-Borivali stretch of 8.2 kms of which the work of track shifting & platform change has been carried out at Malad station.

Benefits:  

2. Extension of Harbour line from Goregaon to Borivali 

Project details: The Extension of Harbour line from Goregaon to Borivali is a  project under MUTP-III-A, covering a length of 7 track kilometres at an estimated cost of Rs.826 crores. Work of land acquisition for the same is currently in progress with a Target Date of Completion  by March-2027

Benefits: 

3. Borivali-Virar 5th & 6th line Project

Project details: The Borivali-Virar 5th & 6th line is a project under MUTP-III-A, covering a length of 26 track kilometres at an estimated cost of Rs.2,184 crores. The Target Date of Completion by December-2027. This project is being executed by MRVC

   Benefits:  

4. Virar-Dahanu 3rd  & 4th line Project

Project details: The Virar-Dahanu 3rd  & 4th line is a  project under MUTP-III, covering a length of 64 track kilometres at an estimated cost of Rs.3,587 crores. This project is being executed by MRVC.

Earth work and work on bridges is in progress with a Target Date of Completion  by December-2026.

Benefits:    

5. Naigaon-Juchandra double chord line Project

Project details: The Naigaon-Juchandra double chord line is a project by Western Railway, covering a length of 6 track kilometres at an estimated cost of Rs.176 crores. Work for the same is currently in progress.

Benefits:  