Goregaon-Mulund Link Road Project: First TBM ‘Tulsi’ Excavates 9 Metres For Twin Tunnels Under SGNP
The first TBM, ‘Tulsi’, for the Goregaon-Mulund Link Road has excavated nine metres for the twin three-lane tunnels beneath SGNP. The Rs 14,000-crore project will connect Goregaon and Mulund through a 12.2-km corridor. The second TBM is 70% assembled and is expected to begin excavation after testing.

The first TBM, ‘Tulsi’, begins excavation for the twin three-lane tunnels of the Goregaon-Mulund Link Road beneath SGNP | AI Generated Image (X - @mybmc)
Mumbai, August 26, 2026: The first tunnel boring machine (TBM) for Phase 3(B) of the Goregaon-Mulund Link Road (GMLR) successfully excavated nine metres for the twin tunnels beneath the Sanjay Gandhi National Park (SGNP), marking a key milestone for the project, the BMC announced on Wednesday.
The project involves constructing twin three-lane tunnels over a 5.30-kilometre stretch between Dadasaheb Phalke Chitranagari (Film City) in Goregaon East and Amar Nagar in Mulund West. The excavations are being carried out using a TBM named ‘Tulsi’, which was commissioned on August 17.
The Rs 14,000-crore GMLR will provide a direct east-west link between Goregaon and Mulund, connecting the western suburbs with the Eastern Express Highway through a 12.2-km corridor.
Tunnelling Progress And Safety
Additional Municipal Commissioner (Projects) Abhijit Bangar inspected the site on Wednesday, reviewing the tunnelling methodology, current excavation progress, related technical aspects and also assessed the safety measures.
"At present, nine meters of excavation has been completed and necessary measures will be taken immediately to maintain the pace of the work and additional manpower will be made available as required. At the same time, clear instructions are given to concerned officials to strictly implement safety rules by giving top priority to the safety of the workers as the work of tunnel excavation is highly technical and challenging," Bangar said.
Meanwhile, 70 per cent of the assembly of the second TBM’s components is completed and officials are directed to finalise the entire assembly by September 30, 2026.
Following this, the Site Acceptance Test (SAT) will begin on October 1 to verify the machinery’s efficient and safe operation, ensuring all systems perform cohesively before commencing excavation.
Also Watch:
ALSO READ
Four-Phase Project
Spanning a total distance of 12.2 km, the project consists of four phases, with the first phase involving road widening, followed by a second phase comprising flyover construction in the western suburbs along with the TBM-driven tunnels.
The third phase includes a road-over-bridge at Nahur, connecting to the final phase, which is an elevated flyover with clover-leaf interchanges up to Airoli. The project is expected to be executed by the end of 2028.
To get details on exclusive and budget-friendly property deals in Mumbai & surrounding regions, do visit: https://budgetproperties.in/
RECENT STORIES
-
Assam Rifles, DRI Seize Yaba Tablets Worth ₹168 Crore In Cachar; 1 Held -
Mumbai Coastal Road North Project: BMC Pushes 60-Km Versova-Bhayandar Link Towards December 2028... -
Shiv Sena Launches 'Mission Gen Z', Brings 250 Young Representatives Together In Mumbai -
Goregaon-Mulund Link Road Project: First TBM ‘Tulsi’ Excavates 9 Metres For Twin Tunnels Under... -
Nepal Appreciates PM Modi's Solidarity, Humanitarian Assistance Offer Amid Devastating Flash Floods
