Mumbai’s ₹11,166 Crore Desalination Project Advances As BMC Seeks MMB, MPCB Clearances
BMC has initiated the process of securing MMB and MPCB approvals for Mumbai’s proposed Rs 11,166 crore desalination project at Manori after receiving CRZ clearance. The project, aimed at strengthening long-term water security, will begin with a 200 MLD plant expandable to 400 MLD.

BMC’s proposed desalination plant at Manori is moving towards the next approval stage to strengthen Mumbai’s future water supply | File Photo
Mumbai, May 9: After securing a key milestone with Coastal Regulation Zone (CRZ) clearance for its proposed 400 Million Litres per day (MLD) seawater reverse osmosis (SWRO) desalination plant at Manori village in the west, the Brihanmumbai Municipal Corporation (BMC) has advanced to the next stage of regulatory approvals.
The civic body has now initiated the process of obtaining permissions from the Maharashtra Maritime Board (MMB) and the Maharashtra Pollution Control Board (MPCB), which are crucial to move the project forward.
BMC secures CRZ clearance for project
Earlier, the BMC secured approval from the Maharashtra Coastal Zone Management Authority (MCZMA) in 2023 through an offline process, followed by online clearance in April after procedural revisions.
The mandatory CRZ clearance from the Expert Appraisal Committee of the Ministry of Environment, Forest and Climate Change (MoEFCC) was obtained by the end of April.
Approvals from the MMB and the MPCB are also required for desalination projects, given their environmental implications — particularly seawater intake and the discharge of concentrated brine — ensuring full compliance with state environmental regulations and the CRZ Notification.
Groundwork and survey process underway
"We are in the process of obtaining two key approvals — MMB and MPCB — after which groundwork can begin. A drone survey has been completed, and land at Manori has been handed over by the state, with formalities underway.
Desalinated water will be conveyed from Manori to Charkop and onward to the tunnel shaft at Mahavir Nagar in Kandivali. A tender for the conveyance tunnel has also been floated,” a senior official said.
Project aimed at strengthening water security
Amid concerns that El Niño conditions could lead to below-normal monsoon rainfall in Mumbai and across Maharashtra, the proposed desalination plant — the state’s first large-scale potable water project — is being positioned as a key measure to strengthen the city’s long-term water security.
The BMC awarded the contract to GVPR Engineers Limited in December 2025.
The project will be implemented in phases, beginning with a 200 MLD facility that is scalable up to 400 MLD.
Also Watch:
ALSO READ
It is estimated to cost Rs 11,166.17 crore, including around Rs 4,077 crore for construction, along with 20 years of operations and maintenance, power costs, taxes and full lifecycle expenses.
To get details on exclusive and budget-friendly property deals in Mumbai & surrounding regions, do visit: https://budgetproperties.in/
RECENT STORIES
-
Mumbai’s ₹11,166 Crore Desalination Project Advances As BMC Seeks MMB, MPCB Clearances -
Jabalpur High Court Reduces Death Penalty To 25-Year Jail Term In Child Rape-Murder Case -
Mother's Day Special: Senior Cop Dipshikha Ware On Sacrifices, Support And Parenting -
Illegal Acid Factory Operating In Sanawadiya Was Sealed Under Directives Of Collector Shivam Verma... -
Mothers' Day Special: Working Women Share Their Struggle Of Balancing Career And Home