Mumbai Infra Update: Mahalaxmi Cable Stayed Flyover Takes Shape, BMC Sets October 2026 Deadline
Construction of the cable-stayed flyover near Mahalaxmi Railway Station is progressing steadily, with over half the pylon work completed. Additional Municipal Commissioner Abhijit Bangar inspected the site and directed officials to maintain safety, quality and timelines. The flyover, spanning key rail and road corridors, is scheduled for full completion by October 31, 2026.
Mumbai: Mahalaxmi Cable Stayed Flyover Takes Shape, BMC Sets October 2026 Deadline |
Construction of the cable stayed flyover on Keshavrao Jedhe Marg near Mahalaxmi Railway Station is moving at a steady pace, with senior civic officials reviewing progress and timelines on site. Additional Municipal Commissioner Projects Abhijit Bangar inspected the bridge work on Thursday and issued a series of instructions to ensure the project is completed within the committed deadline.
Pylon Work Crosses Halfway Mark
A key highlight of the project is the towering 78.5 metre high steel pylon that will support the cable stayed structure. Civic officials confirmed that nearly 55 per cent of the pylon work has already been completed. During the inspection, Bangar stressed the need for detailed planning so that the pylon, approach roads and all associated works are completed in a coordinated manner. He directed officials to ensure the entire flyover is fully operational by October 31, 2026.
Emphasising public safety, Bangar instructed the project team to strictly adhere to safety norms, quality control processes and technical inspections throughout the construction phase.
ALSO READ
Span Construction and Railway Coordination
The flyover will feature two independent spans extending from the central pylon. The western span, measuring 95 metres, is scheduled to be completed by the end of February 2026. Work on this stretch is progressing as planned.
The eastern span, which will extend 165 metres, falls within the railway boundary. Its construction will begin only after the required block is obtained from the railway department. Officials said the erection of this span is expected to commence after approvals and is planned to be completed between March 15, 2026, and October 15, 2026.
Focus on Timely Completion Despite Monsoon
The Bridge Department has been instructed to work closely with the local ward office and traffic police to minimise disruption and speed up execution. Bangar directed officials to finalise a detailed work schedule and to undertake parallel activities wherever possible to save time.
He also stressed that planning must account for the monsoon season, ensuring that work does not come to a halt during heavy rains. All ancillary works related to the flyover are to be completed alongside the main structure by the October 2026 deadline.
Deputy Commissioner Infrastructure Girish Nikam, Executive Engineer Bridge Rajesh Mulye and other senior engineers were present during the inspection.
To get details on exclusive and budget-friendly property deals in Mumbai & surrounding regions, do visit: https://budgetproperties.in/
RECENT STORIES
-
Mumbai News: 2 Dogs Sexually Abused In City, Animal Activists Demand Amendments To BNS And PCA For... -
'Is The CM So Helpless?': Bombay HC Questions State As Minister’s Son Evades Arrest In Mahad Poll... -
First Tamil Nadu, Then Kerala & Now Karnataka: MK Stalin Says Time To End Governor’s Address -
Mumbai Crime: ₹11.21 Crore Corporate Fraud Uncovered At Sion-Based Export Firm; EOW Probes Role Of... -
Mumbai News: Fish Traders From Dadar Shifted To Crawford Market After Bombay High Court Order