Mumbai: SCDRC awards 5 lakh compensation to home buyer
Ashwin and Alka Joshi, residents of Mulund, had booked a flat in a saleable component of an SRA redevelopment scheme
Mumbai: The state Consumer District Redressal Commission (SCDRC), Maharashtra, directed that a flat buyer be compensated with Rs 5 lakh for the mental agony they faced for not getting possession of the flat they had booked.
The order was passed on August 11 by Justice SP Tavade, president and AZ Khwaja, judicial member, SCRDC.
Ashwin and Alka Joshi, residents of Mulund, had booked a flat in a saleable component of an SRA redevelopment scheme. They booked a flat measuring 515.80 sq ft.
However, even after paying almost the entire amount, they did not get possession of the flat. The Joshis had paid a total of Rs 64.10 lakh, which included Rs 15 lakh that they had taken as bank loan.
When they did not get the flat, they complained that the developer should not have taken the money till the occupation certificate (OC) was in place and that the flat's possession should have been given on time.
M/s S Siddharth Constructions Co argued that there was no date given and that the Johis were informed in advance that being an SRA project, there would be a delay.
The commission observed that agreement may not have had a date but later correspondences did mention about it. It thus found deficiency in service and unfair trade practice by the construction company.
RECENT STORIES
-
MP Weather Update: Temperatures Soar Upto 43°C On Polling Day; Heatwave Alert For May 8 -
Noida: AAP MLA Amanatullah Khan, Son Booked For Threatening & Assaulting Petrol Pump Workers After... -
Richa Chadha Roasts Heeramandi Co-Star Sharmin Segal: ‘Don’t Think You & I Should Sit Next To... -
Madhya Pradesh Lok Sabha Election 2024 Phase 3 LIVE: Jyotiraditya Scindia, Arif Masood Cast Votes;... -
Mumbai: Oberoi Realty And Purvankara Developers Appointed To Redevelop Premium Projects In City