Mumbai Road Concretisation: Open Sewer Chamber Found During Inspection In Malad; BMC Warns Officials, Sets May 31 Deadline
During a surprise inspection of the road concretisation work on Thursday night, senior civic officials found that the chamber related to sewerage operations was left open, neglecting safety measures and risking lives. Taking a serious note of it, the Additional Commissioner Abhijit Bangar instructed the officials to issue a notice to the concerned engineer and take strict action.

Additional Commissioner Abhijit Bangar inspects road concretisation work in Malad, directs action on safety lapses | X -@mybmc
Mumbai: During a surprise inspection of the road concretisation work on Thursday night, senior civic officials found that the chamber related to sewerage operations was left open, neglecting safety measures and risking lives.
Taking a serious note of it, the Additional Commissioner Abhijit Bangar instructed the officials to issue a notice to the concerned engineer and take strict action against the negligence.
Bangar inspected concretisation of roads in the Western suburbs such as Ramchandra Marg in Malad West, Parekh Gali in Kandivli West, and Mahavir Nagar Marg. During this visit, he observed the ongoing works on Dadi Seth Marg in Malad West, where, in addition to the concretisation work, the sewage cleaning work were also underway. However, Bangar noticed negligence concerning the chambers, which led to immediate instructions for corrective action.
He also instructed to compete the concretisation of ongoing roads before May 31. Bangar stressed the importance of micro-planning to establish clear completion deadlines for each road segment. Furthermore, he instructed that the work be completed from one end of the road to the other without leaving any part unfinished.
Bangar instructed to put necessary barricades at key locations to ensure smooth traffic flow and prevent any disruption. Additionally, he directed that construction debris be managed properly to avoid it scattering around.
He conducted the slump and cone tests at the worksite, and the results were found to be satisfactory. Additionally, the team from the Indian Institute of Technology (IIT) Mumbai conducted a 'Cube Test' for Pavement Quality Concrete (PQC) samples at the laboratory on site.
ALSO READ
The results of thes tests were also found to be within acceptable standards. "The roads where the concretisation work has been completed should have thermoplastic markings, zebra crossings, cat eyes, and yellow thermoplastic grid markings at intersections, said Bangar.
RECENT STORIES
-
Telangana: Neurosurgeon Charred To Death After Car Crashes Into Divider, Catches Fire -
Hina Khan Revisits Kashmiri Childhood Memory Of Fresh Walnuts; Know The Difference Between Fresh &... -
Navi Mumbai Professor To Present Research On Gender, Ecology And Literature At International... -
'One In A Billion Chance': Father & Son Sailors Cross Paths In The Middle Of The Ocean; Heartwarming... -
Mumbai Crime: 23-Year-Old Man Takes ₹60K Loan, Loses ₹56 Lakh After Scammers Threaten To Leak...