Mumbai: BMC Prepares To Connect Coastal Road With Worli-Bandra Sea Link
Spanning 850 meters, the linkage between the coastal road's Worli terminus and the sea link primarily consists of 270 meters of steel and the remainder concrete.

Mumbai: The Brihanmumbai Municipal Corporation (BMC) has taken a significant step forward in its coastal road project by loading a 2000 metric tonne, 136-meter span bowstring arch onto a barge at Mazgaon Dock Jetty (Nhava) on Sunday.
This prefabricated and pre assembled structure is set to connect the coastal road with the Bandra Worli Sea Link, aiming to alleviate southbound traffic congestion.
ALSO READ
The connection between the southbound arm of the Coastal Road and the Bandra-Worli Sea Link is scheduled to be completed by April 17, filling a crucial gap in Mumbai's coastal infrastructure.
ALSO READ
Spanning 850 meters, the linkage between the coastal road's Worli terminus and the sea link primarily consists of 270 meters of steel and the remainder concrete.
RECENT STORIES
-
Mumbai News: GLC And D M Harish Foundation To Host Panel On West Asia Conflict And Future Of... -
Bhopal Amrut Project: BMC Moves To Secure ₹450 Crore Loan From World Bank -
Indore News: Free Rabies Treatment Rolled Out Across Health Centres -
Mumbai News: BMC Gets MCZMA Nod For ₹11,166 Crore Manori Desalination Plant, Awaits Final MoEFCC... -
Bombay HC Allows 3 JBIMS Students To Appear For Exams Despite Admission Cancellation