GAIL Discharges First LNG Vessel At Dabhol LNG Terminal; GAIL To expand Terminal’s Capacity From 5.0 MMTPA to 6.3 MMTPA
With the commissioning of the breakwater after receipt of all statutory approvals, Dabhol LNG Terminal has now been designated an all-weather port, which is a critical transformation that ensures safe and reliable LNG operations even during the southwest monsoon, traditionally a challenging period for marine logistics on India’s west coast.

File Image |
Dabhol: GAIL (India) Limited has successfully berthed and discharged its first LNG vessel at the Dabhol LNG Terminal following the completion of the landmark Breakwater Project.
The vessel, GAIL Bhuwan, was received on June 2, 2025, by Shri Sandeep Kumar Gupta, Chairman & Managing Director, and Shri Sanjay Kumar, Director (Marketing), GAIL, marking the commencement of uninterrupted, round-the-year operations at the terminal.
With the commissioning of the breakwater after receipt of all statutory approvals, Dabhol LNG Terminal has now been designated an all-weather port which is a critical transformation that ensures safe and reliable LNG operations even during the Southwest monsoon, traditionally a challenging period for marine logistics on India’s West coast.
Strategically located on the Maharashtra coastline, the Dabhol LNG Terminal has a regasification capacity of 5.0 MMTPA and serves as a vital link in India’s gas supply network via the Dabhol-Bangalore and Dabhol-Panvel cross-country pipelines.
Dabhol is an island breakwater (unlike conventional land-connected structures) showcasing a feat of advanced marine engineering. This ambitious project, involving extensive collaboration among multiple stakeholders, posed complex technical challenges and required innovative, customized solutions.
The successful commissioning of the breakwater is expected to significantly enhance vessel accessibility and improve capacity utilization at the terminal, bolstering energy infrastructure and supply reliability.This achievement comes at a crucial time as GAIL looks to expand the terminal’s capacity from 5.0 MMTPA to 6.3 MMTPA in the first phase over the next three years.
Once expanded, the terminal is expected to handle up to 100 LNG cargoes annually, thereby playing a pivotal role in reinforcing India’s energy security.Pic Caption: Sh. Sandeep Kumar Gupta, CMD, GAIL and Sh.
Sanjay Kumar, Director (Marketing), GAIL receiving 1st LNG vessel at the all-weather Dabhol LNG terminal during monsoon season.
RECENT STORIES
-
Madhya Pradesh Police Transfers: 25 Officers Transfered; Gadarwara SDOP Shubmam Singh Thakur... -
Pakistani Journalist Shaukat Piracha's X Account Withheld In India While He Attends SCO Forum In... -
Hyundai Cars To Get Costlier By Up To ₹8,000 From December 1, Rising Input Costs Trigger Price... -
ICC Refuses To Lift Saliva Ban On Cricket Balls Despite India's Captain Shubman Gill's Demand,... -
Two Months After Sahil Wakode's Death, IIT-Bombay Begins Replacing Ceiling Fans With Wall-Mounted...