Colaba-Bandra-SEEPZ Metro-3 Corridor: MMRC begins high voltage charging for 8 coaches of first train

After receiving the eight coaches from Sri City, Andhra Pradesh, a battery-operated rail-cum-road shunter – a first procurement for the MMRC Car Depot – has successfully formed the first 8-car prototype train at the temporary facility – the Train Delivery & Testing Track area – in Sariput Nagar, Aarey.

Sweety Adimulam Updated: Tuesday, August 16, 2022, 09:03 PM IST

The Mumbai Metro Rail Corporation (MMRC), which is the project implementing authority for the underground Metro 3 (Colaba-Bandra-SEEPZ), initiated high voltage charging (25KV) for the eight coaches of its first prototype train.

According to the MMRC, charging of every train is a daily and never-ending activity and after charging the train at a high voltage of 25KV AC, static functionality tests of all the sub-systems, such as functioning of air-conditioners, the communication system including speakers and the public address system etc. of the train will be taken up. It is only after successful completion of these tests that the train will be ready for the dynamic design proving trials.

After receiving the eight coaches from Sri City, Andhra Pradesh, a battery-operated rail-cum-road shunter – a first procurement for the MMRC Car Depot – has successfully formed the first 8-car prototype train at the temporary facility – the Train Delivery & Testing Track area – in Sariput Nagar, Aarey.

The corporation expects to begin initial design proving trial runs of the train in the last week of August in the 3-km stretch of the MML3 tunnel from the temporary facility to Marol Naka metro station.

Meanwhile, the MMRC has geared up with the depot work to begin the operation of Phase 1 as targeted by December 2023. It is aiming to get the depot ready by April next year.