Indore Metro Underground Project Sets New Record With 11 Tunnel Rings Installed In A Day, 90 Metres Of Tunnelling Completed
Indore Metro's underground project achieved a milestone by installing 11 precast concrete tunnel rings in one day, exceeding its usual target of eight to nine. Minister Kailash Vijayvargiya inspected the Airport Road site, where approximately 90 metres of tunnelling is complete. He said underground construction could take two more years.

Indore Metro Underground Project Sets New Record With 11 Tunnel Rings Installed In A Day, 90 Metres Of Tunnelling Completed | Representative image
Indore (Madhya Pradesh): While traffic continues to move normally on busy Airport Road, engineers are carving out a metro tunnel nearly 20 metres beneath the surface. The Indore Metro underground project has achieved a milestone by installing 11 precast concrete rings in a single day, surpassing the usual daily target of eight to nine rings.
Urban development and housing minister Kailash Vijayvargiya inspected the construction site around 5 pm on Wednesday and reviewed the project's progress.
During the inspection, Vijayvargiya said approximately 90 metres of the underground tunnel had been completed. Advanced tunnel boring machines (TBMs) are being used to accelerate construction while maintaining engineering standards and safety measures.
Despite the rapid progress, the minister said completing the entire underground tunnel and associated technical works would take approximately two more years.
Traffic above, tunnelling below
Vijayvargiya said construction was progressing nearly 20 metres underground without disrupting traffic or daily activities on the surface. Even residents of nearby buildings were largely unaware of the massive tunnelling operations beneath them.
He said activities above ground remained unaffected despite vibrations generated during excavation.
The minister also held discussions with Metro general manager Rajput, engineers from Hindustan Construction Company (HCC) and other technical experts to review progress.
Appreciating the workers' dedication, Vijayvargiya said several engineers and employees would continue working even during Diwali, sacrificing celebrations with their families to maintain the project's momentum.
ALSO READ
RECENT STORIES
-
Dalal Street Rallies Ahead Of Diwali: Sensex Soars Nearly 1,400 Points, Nifty Crosses 24,300 -
Virat Kohli Turns 38: 'King Kohli' Receives Heartwarming Birthday Wishes As Cricket Fraternity And... -
Canva's Severance Package For Laid-Off Employees Wins Praise Online: Here's What It Entails -
OpenAI Acquires Pierre Computer Company To Expand Codex AI Coding Tools & Strengthen AI-Powered... -
Bengaluru Woman Presses Accelerator Instead Of Brakes, SUV Crashes Into Kebab Centre; 3 Suffer Burns...