The Bombay City Civil Court has ordered builder Sanjay Bhalerao and two firms to jointly repay Rs 4.10 crore to seven Bhatia family members, with 9% annual interest and costs. The family had invested in two real estate projects but alleged that construction and repayment never materialised.

Add FPJ As a
Trusted Source
Mumbai Court Orders Builder And 2 Firms To Pay ₹4.10 Crore To 7 Members Of Bhatia Family
FPJ News Service Updated: Friday, October 30, 2026, 11:16 PM IST
Mumbai Court Orders Builder And 2 Firms To Pay ₹4.10 Crore To 7 Members Of Bhatia Family

The Bombay City Civil Court has directed the builder and two firms to repay seven members of the Bhatia family with nine per cent annual interest | Representational Image

Mumbai, October 30, 2026: The Bombay City Civil Court, Mazgaon, has directed builder Sanjay Bhalerao and three others to pay Rs 4.10 crore to seven members of the Bhatia family after they failed to repay money invested in two real estate projects.

The city civil judge was hearing a suit filed by family members of two brothers, Naresh Bhatia and Manish Bhatia, through their lawyer, Rajesh Vanzara, against Bhalerao and two firms, S.D. Bhalerao Associates and Aditya Enterprises Project Vartak Nagar Builders & Developers.

The court allowed the suit and directed the defendants to jointly and severally pay Rs 4.10 crore with 9 per cent annual interest from the date of filing of the suit until realisation, besides costs.

Investment In Real Estate Projects

According to the plaintiffs, they met Bhalerao in 2011, when he allegedly induced them to invest their lifetime savings in the Vartak Nagar Deepmala and Preeti Park projects, promising 12 per cent annual interest and issuing promissory notes.

However, the defendants allegedly failed to undertake construction or refund the investments. The court noted that Bhalerao subsequently agreed to refund Rs 72 lakh against an investment of Rs 60 lakh and also issued cheques towards repayment. The cheques worth Rs 4.10 crore were dishonoured.

Also Watch:

Court Orders Repayment

Hence, the Bhatia family issued a notice for cheque bouncing and also filed a suit in June 2021 for recovery of the amount invested.

On July 13, 2026, the court asked the defendants to deposit Rs 2.05 crore within two months. However, they failed to comply. Hence, the court allowed the suit filed by the Bhatia family against Bhalerao and the two firms.