Uttarkashi Tunnel Rescue Latest Update: Ambulances Ready, Road Being Repaired To Rush Workers Trapped In Silkyara To Hospital
A separate ward comprising 41 oxygen-supported beds has been readied at the community health centre in Chinyalisaur, about 30 km from Silkyara, for the workers.

Ambulances Ready, Road Being Repaired To Rush Workers Trapped In Silkyara To Hospital | Twitter
Uttarkashi, November 28: With just five metres left to achieve a breakthrough in digging through the rubble of the Silkyara tunnel, preparations got underway on Tuesday to rush the trapped workers to a hospital for immediate medical care following their rescue. A separate ward comprising 41 oxygen-supported beds has been readied at the community health centre in Chinyalisaur, about 30 km from Silkyara, for the workers.
The road outside the tunnel became uneven due to regular movement of heavy vehicles
The road outside the tunnel, which became uneven due to regular movement of heavy vehicles over the past fortnight was being repaired and a fresh layer of soil was being laid for smooth movement of ambulances.
Senior police officers briefed the security personnel outside the tunnel to spring into action
Senior police officers briefed the security personnel outside the tunnel to spring into action the moment workers started coming out of the escape passage being prepared for them. Pipes have been inserted up to 52 metres through the rubble at Silkyara tunnel, Uttarakhand Chief Minister Pushkar Singh Dhami said on Tuesday as efforts to rescue the 41 workers trapped there continued for the 17th day. The breakthrough point is 57 metres, he told reporters in Silkyara.
Rescuers need to dig through around 10 metres of rubble
Rescuers need to dig through around 10 metres of rubble using rat-hole mining techniques to bring out the workers. This drilling was earlier carried out by a huge auger machine that got stuck in the rubble on Friday at around 47 metres.
A skilled team of workers began removing the muck by hand
A skilled team of workers began removing the muck by hand using the rat-hole mining technique on Monday while 800-mm diameter pipes were being pushed through the rubble by an auger machine.
'Pipe has gone in up to 52 metres'
"Pipe has gone in up to 52 metres. Earlier, it was at 51 metres. It was pushed one metre further in my presence. It will be pushed two metres more to 54 metres after which one more pipe will be laid," Dhami said.
Steel and iron girders were not being encountered
When asked whether there were hurdles on the way, he said steel and iron girders were not being encountered. "Stones are coming in the way but they are being broken using cutters," the chief minister said.
ALSO READ
RECENT STORIES
-
Dhirubhai Ambani International School Ranks 9th Among IBDP Schools Worldwide; Only Indian School In... -
Kyunki Saas Bhi Kabhi Bahu Thi 2, October 1 Written Update: Navratri Function Turns Dramatic As... -
PKL 12: U Mumba Complete Double Over Tamil Thalaivas, Move To 5th After Sandeep Produces Masterclass -
Dussehra 2025: Defence Minister Rajnath Singh To Celebrate Festival With Soldiers In Gujarat's Bhuj -
‘Dirty Mentality’: Mumbai Sessions Court Sentences 40-Year-Old Man To Life Imprisonment For...