Mumbai Is Now 400 KV National Grid Integrated

Mumbai Is Now 400 KV National Grid Integrated

With this project’s commissioning, Mumbai gets a 400 KV grid within its municipal geography, bringing enhanced import capability within its electricity grid and improving reliability and stability.

FPJ News ServiceUpdated: Tuesday, October 03, 2023, 08:21 AM IST
article-image
Mumbai Is Now 400 KV National Grid Integrated |

Ahmedabad: Kharghar Vikhroli Transmission Limited (KVTL), which will enable additional power to be brought into Mumbai and thus enable in meeting the city’s growing and future electricity demand, is commissioned. Built by Adani Energy Solutions Limited (earlier known as Adani Transmission Limited), the energy solution, transmission and distribution arm of the Adani portfolio, the project is critical for Mumbai as the existing capacity of the transmission corridor is not sufficient to carry further power into the city.

Mumbai witnessed grid failure twice in recent times – on 27 February 2022, and on 12 October 2020; localities across the metropolis went dark for a considerable period. The Kharghar-Vikhroli line will bring additional 1,000 MW reliable power to Mumbai city as a solution to mitigate any such incidents in the future. With this project’s commissioning, Mumbai gets a 400 KV grid within its municipal geography, bringing enhanced import capability within its electricity grid and improving reliability and stability. For consumers, it provides that much more sustainability to commuting through bullet trains, Metro Rail and city railways, as also for commercial and residential establishments.

KVTL comprises approximately 74 circuit kilometres of 400 kV and 220 kV transmission lines, along with a 1,500 MVA 400kV Gas Insulated Substation (GIS) at Vikhroli, the first 400KV substation of its kind in Mumbai. Occupying approximately 9,500 sq m area, it has the most compact design when it comes to 400 KV substations. Its unique design vertically stacks 400kV and 220kV GIS, thus minimizing space requirements.

AESL braved a number of challenges while laying the line, mainly in surmounting difficult terrain, but these were overcome with the use of technology and innovation. For instance, six towers were constructed in creeks using heavy rigs on floating barges. In urban areas, height restrictions in some locations were overcome by adopting special horizontal configuration towers.

The KVTL project starts in the Kharghar area of Navi Mumbai, traverses through its urban locations and terminates at Vikhroli in Mumbai city. 

RECENT STORIES

Who Was Roshni Songhare? Air India Crew Member From Dombivli Dies In Ahmedabad Plane Crash

Who Was Roshni Songhare? Air India Crew Member From Dombivli Dies In Ahmedabad Plane Crash

Mumbai Guide: Bet You Didn't Know About THESE Underrated Spots In City

Mumbai Guide: Bet You Didn't Know About THESE Underrated Spots In City

BMC Vows Strict Penalties As Private Contractors Caught Dumping Waste On Roads In Eastern Suburbs

BMC Vows Strict Penalties As Private Contractors Caught Dumping Waste On Roads In Eastern Suburbs

MCOCA Court Grants Bail To Salim Penwala In 2011 Extortion Case Citing Lack Of Direct Evidence

MCOCA Court Grants Bail To Salim Penwala In 2011 Extortion Case Citing Lack Of Direct Evidence

Retired BMC Official Duped Of ₹1.53 Crore, Policeman Loses ₹6 Lakh In Separate Cyber Frauds

Retired BMC Official Duped Of ₹1.53 Crore, Policeman Loses ₹6 Lakh In Separate Cyber Frauds