Mumbai : Power-to-airports major GMR Group has approached IDBI Bank, the lead bank to GMR Rajahmundry Energy, to reschedule its Rs 2,600-crore loan.

The group has also asked the lenders to allow the company to delay the commissioning of the project to April, 2014.             “We have requested the lenders consortium, led by IDBI Bank, to reschedule the loan to the 768-mw gas-fired power plant at Rajamundry in Andhra (GMR Rajahmundry Energy), due to unavoidable circumstances. We are hopeful that it will be done,” GMR Energy Chief Financial Officer Bhaskar Rao told PTI.

He said this is not a debt restructuring, but rescheduling of a standard loan. The highly-indebted GMR Group has debt of Rs 35,000 crore or 3.2 times its balance sheet size at the end of the second quarter.  The  Rs 3,250-crore, 768-mw coal-fired Rajamundry project has a loan component of                      Rs 2,600 crore taken from 11 banks, Rao added.

Rao said they have asked the lenders to allow the company to delay the commissioning of the project to April 2014 as gas supply issues are yet to be resolved and the civil work not over so far.

(For all the latest News, Mumbai, Entertainment, Cricket, Business and Featured News updates, visit Free Press Journal. Also, follow us on Twitter and Instagram and do like our Facebook page for continuous updates on the go)

Free Press Journal

www.freepressjournal.in